Niger oil pipeline project PMC project

Project Overview: the design flow is 100x 104t/a, the design pressure is 10MPa,the whole line is 462.15km long, and the pipe diameter is 323.9mm. It has first station, last station and 5 intermediate heating stations as well as 7 line cut-off valve houses.
Work Scope: responsible for the supervision and management of prospecting and surveying, preliminary design, long-term procurement support, EPC bid evaluation and detailed design, procurement, construction, commissioning, quality assurance, etc. in the whole cycle of the project, etc.
Work Duration: May 1, 2009-Dec. 31, 2011
Project Honor: National High-quality Project Award in 2013 granted by China Association of Construction Enterprise Management
High-quality Petroleum Project Gold Award (Overseas) in 2013 granted by China National Petroleum Corporation.