PMC Project (Phase I) of Chad Crude Oil Pipeline Project
Inputtime:2019-06-06 13:43:40

Project Overview: the pipeline is 320 km long with 1 first station, 1 last station and 8 line valve houses (including 4 RTU valve houses) along the line.
Work Scope: responsible for preliminary design, preparation of EPC bidding documents, support for bid evaluation, compilation of the employer's bidding documents for procured items, support for procurement, project coordination and management, supervision of detailed design, procurement supervision, construction supervision, supervision of commissioning, putting into production and warranty period, and support for handover of as-built drawings and works, etc.
Work Duration: Apr. 10, 2009-Jul. 31, 2011
Project Honor: High-quality Petroleum Project Gold Award (Overseas) in 2014